ge Theater on the Move CALT CAUTION CAUTION THE K PALACE THEATER PROGRESS REPORT #4 Plumbing and Electrical inspection is complete and we passed! Framing has begun which includes finishing the flooring, dry-walling the seating area, the bar and restrooms. Once complete, lighting will be installed and the stage will be built. The HVAC folks will be in soon to inspect and service the HVAC and to add updated digital thermostats. Street side and building signs have been designed, and are being built. They should be installed by mid July. We will keep you informed each month on our progress. We'll be opening soon, "the good Lord willin' and the creek don't rise!" (One of my Mom's favorite sayings). v/r Tommy Kelley TION UTION CAUTION ge Theater on the Move CALT CAUTION CAUTION THE K PALACE THEATER PROGRESS REPORT # 4 Plumbing and Electrical inspection is complete and we passed ! Framing has begun which includes finishing the flooring , dry - walling the seating area , the bar and restrooms . Once complete , lighting will be installed and the stage will be built . The HVAC folks will be in soon to inspect and service the HVAC and to add updated digital thermostats . Street side and building signs have been designed , and are being built . They should be installed by mid July . We will keep you informed each month on our progress . We'll be opening soon , " the good Lord willin ' and the creek don't rise ! " ( One of my Mom's favorite sayings ) . v / r Tommy Kelley TION UTION CAUTION